WISCONSIN – American Transmission Co. (ATC) energized the Spring Valley-North Lake Geneva Electric Reliability project, a new transmission line that now electrically connects Kenosha County with the Lake Geneva area.
The project included construction of a new 23-mile 138 kV transmission line, construction of the new Balsam Substation along Wisconsin State Trunk Highway 50 in the town of Wheatland, and construction of a new 69 kV transmission line to connect the new substation to the Twin Lakes Substation in Twin Lakes.
The total value of the project was $71 million.