Photo: Siemens press picture
German transmission grid operator TransnetBW has commissioned Siemens to build new switchgear in the 380 kilovolt (kV) Daxlanden substation in Karlsruhe, Baden-Württemberg.
Two new gas-insulated indoor switchgear, initially with 26 panels, will boost the substation's transmission capacity and cover the increased transport demand in the German high-voltage grid as a result of the transition to a new energy mix.
In the future, it will thus be possible to transport large quantities of wind energy from northern Germany to the southern part of the country.
The commissioning of the turnkey solution will take place in stages and be completed in 2029.
The order is priced in the low triple-digit millions range.
Source: Siemens