TEXAS – The Southwestern Electric Power Company (SWEPCO) is preparing to rebuild a five-mile stretch of its $27 million transmission line project in Texarkana, Texas, over the next year.
This third phase of the 11-mile should run into spring 2021 and achieve full completion that summer, reports Daily Energy Insider.
The five miles being worked on in this phase cover an intersection at West 39th and Walnut streets in northeast Texarkana to the intersection of Summerhill Road and Clear Creek Dr.
A fourth and final phase will follow in early 2021 and include work on 1.5 miles of transmission line in the area of Clear Creek, Summerhill Road, and Gin Road.
All work should conclude by summer 2021.
Source: Daily Energy Insider